Moving and resizing jobs in the Job calendar

This feature was added in vintrace Version 6.1.1

In countries outside of USA, a Work Order is referred to as a Cellar Note. In keeping with regional terminology differences, please substitute Work Order for Cellar Note below.

Please note that any fruit booking option is only available in vintrace Professional package while any production job option is only available in vintrace Enterprise package.

The job calendar allows you to move jobs between different dates and times and also to resize jobs to increase or decrease the duration.

Moving a job to a new date and time

In month view, you can move a job by dragging and dropping it to a new date. In the example below, we are moving a job from 17th June to 23rd June.

Month view move task

A message is displayed to confirm the new date/time of the job. In month view, you can only move the job to a new date, the time will be the same.

Click on Ok button.

Confirm task move month view

The job is moved to the new date/time.

Month view task moved successfully

In week view, you have the option to move a job to a new date and time, and resize a job to change the duration.

You can move a job by dragging and dropping it to a new date. In the example below we are moving a job from 8th June, 9am to 9th June, 2pm.

Week view move task

A message is displayed to confirm the new date/time of the job. Click on Ok button.

Week view confirm move task

The job is moved to the new date and time.

Week view task moved successfully

Moving a job to a new time within the same day

You can change the time of the job within the same day by moving it up/down the calendar. This is available for week view and day view.

In the following example, we are moving a job from 2pm to 12pm.

Week view move task to new time

A message is displayed to confirm the new date/time of the job.Click on Ok button.

Week view confirm move time

The job is moved to the new time.

Week view moved to new time successfully

Changing the expected duration of a job (resizing)

In week view and day view, you can also change the duration of a job by resizing it. To resize a job, drag the bottom border of the job downwards to increase the duration or upwards to decrease the duration. In the example below, we are increasing the duration of a job from 2 hours to 4 hours.

Week view resize task

A message is displayed to confirm the new date/time of the job.Click on Ok button.

Week view confirm resize

The duration of the job is changed successfully to 4 hours.

Week view resize task successful